I'm a

Central Interceptor

The largest wastewater project in New Zealand, our super-sized tunnel will run for 16.2kms under Auckland city and the Manukau Harbour. Find out what it’s all about and how we’re tracking.

Duration

2019-2026

Location

Herne Bay to Māngere

Status

Construction

The end is in sight for the Central Interceptor project

With a planned ‘ready to commission’ timeline of mid-2026, the northern section of the tunnel can ‘go-live’ to connect up to the southern section, which commenced operation in February 2025.

The first Northern construction site to be completed was Walmsley Park in Mt Roskill. This public space has been reinstated with new planting and was handed back to Council Parks to open in December last year.


Central Interceptor's reinstatement team underway with new planting

CI_reinstatement_team_underway_with_new_planting.png

The next three sites to be completed lie on the 2.1km Link Sewer B: Mt Albert War Memorial Reserve is about to have the carpark spaces repainted and will soon be reopened for visitors. (See image). The other two sites are Norgrove Reserve and Rawalpindi Reserve, further along Meola Creek, which are nearing the end of their reinstatement works. And Lyon Ave, on the Roy Clements Treeway north of Kerr-Taylor Park is close to completion also.

Four sites will take until mid-year to complete their work programmes and be handed to the reinstatement/replanting team (see image): Haverstock Rd in Sandringham, Western Springs, Tawariki St (on Watercare land in Grey Lynn) and Point Erin Park, Herne Bay.

Last to finish is our main tunnel site at May Road in Mt Roskill. Wastewater from Miranda Reserve in Avondale is already flowing along the new Link Sewer C to May Road and on into the southern section of the CI tunnel. After the full tunnel commissioning in mid-2026, May Road’s CI assets, particularly a new air treatment facility, will be passed to Watercare’s Operations team for on-going maintenance, along with all the new infrastructure at 17 sites across the isthmus.

Mt Albert War Memoriral lower carpark restoration


Mt_albert_war_memorial_reserve_lower_carpark_restoration_.png

See how far we've tunnelled

See what our three Tunnel Boring Machines have achieved

What are we building under there?

The Central Interceptor tunnel lies between 15 and 110 metres below the city surface and will run all the way from Pt Erin in Herne Bay to Māngere Wastewater Treatment Plant. With a diameter of 4.5m, the tunnel will be high enough to fit a standing giraffe inside.

Along with two smaller-link sewer tunnels also under construction, the main CI tunnel will collect wastewater from the existing network and take it to Māngere, with a controlled flow rate. The tunnel slopes at a gradient of 1:1000 so wastewater can flow downhill to Māngere.

The budget for this epic seven-year project is $1.668 billion.

Did you know?

The Central Interceptor tunnel has capacity to store more than 250,000 cubic metres of wastewater - that’s 99 Olympic swimming pools. Read more in our project brochure.

Construction updates

We have 17 construction sites along the tunnel route, with some operating for three to five years, with smaller sites open for around 24-36 months.

At the bottom of the page, you can see what’s going on at each site.


The technology behind New Zealand’s largest wastewater project

To dig the main CI tunnel and lay the concrete segments behind it, we used state-of-the-art tunnel boring machines (TBMs). These gigantic machines enable us to excavate (or ‘bore’) through a wide range of ground conditions.

Infrastructure constructed by these powerful TBMs is strong and reliable and is set to last at least 100 years.

Photo of the tunnel boring machine Hiwa-i-te-Rangi being unveiled.

Engaging with locals

We want to update you on the construction process and hear your feedback. If you live or work near one of our sites, you’ll get a bulletin, newsletter, notice or letter, or an invitation to a public event, depending on the information we have to share.

Email us your feedback.


Supporting our wider community

Although it’s being built to last 100 years, the ambition for the project extends well beyond construction. We also want to help improve the wellbeing of communities along the tunnel route.

To support this, a cultural outcomes group is providing advice as the project progresses. This group comprises people from mana whenua, our Watercare team and contractors. Check out some of our activities.


Protecting our environment

As well as delivering significant environmental benefits such as cleaning up our waterways, we’re committed to leaving our construction sites and their surrounds in a better condition than when we arrived.

Updates from our sites across Auckland

Dundale Avenue - Construction began: July 2020

Location: Road Reserve near 66 Dundale Avenue, Blockhouse Bay, Auckland 0600

Dundale Avenue is the launch site for the smaller tunnel boring machine that will take flows from the Western Interceptor and connect them to the new Central Interceptor tunnel at May Road.


Bulletins

Read our latest bulletin

March 2023

July 2022

December 2021

October 2021

June 2020


Sign up for the latest news

Sign up to our Dundale Avenue Bulletin, so you know what’s happening throughout the project.

Frederick Street (PS23) - Construction began: July 2021

Location: 39 Frederick Street, Hillsborough, Auckland 1042

Bulletins

Read the latest Frederick Street bulletin

December 2023

March 2023

March 2021


Sign up for the latest news

Sign up to our Frederick Street bulletin, so you know what’s happening throughout the project.

Haverstock Road - Construction began: April 2022

Location: 98 Haverstock Road, Sandringham, Auckland 1025

Bulletins

Read the latest issue of the bulletin

April 2025

April 2024

September 2023

December 2022

March 2022


Sign up for the latest news

Sign up to our Haverstock Road bulletin, so you know what’s happening throughout the project.

Haycock Avenue - Construction began: May 2020

Location: 4 Haycock Avenue, Mt Roskill, Auckland 1041

Bulletins

Read our latest Haycock Avenue bulletin

December 2022

December 2021

May 2021 issue

May 2020 special edition


Sign up for the latest news

Sign up to our Haycock Avenue bulletin, so you know what’s happening throughout the project.

Keith Hay Park - Construction began: January 2020

Location: ​22 Gregory Place, Mt Roskill, Auckland 1041

Bulletins

Read the latest Keith Hay Park bulletin

August 2024 issue

June 2023 issue

August 2022 issue

December 2021 issue

October 2020 issue

April 2020 issue

November 2019 issue


New CI project
We are beginning construction on a new extension to CI in the Park, to cater for future growth in the area. Read more.

Sign up for the latest news

Sign up to our Keith Hay Park Bulletin, so you know what’s happening throughout the project.

Lyon Avenue - Construction date: May 2022

Location: 30-36 Alberton Avenue (near Lyon Avenue & Morning Star Place), St Lukes, Auckland 1025

Bulletins

Read our latest Lyon Avenue bulletin

August 2024 issue

October 2023 issue

March 2023 issue

February 2022 issue

Sign up for the latest news

Sign up to our Lyon Avenue bulletin, so you know what’s happening throughout the project.

Māngere Pump Station - Construction began: August 2019

Location: Māngere Wastewater Treatment Plant, Māngere, Auckland 2022 (access via Island Road or 75 Greenwood Road)


Bulletins

Read the latest issue of the Māngere Pump Station bulletin

May 2023

August 2022 issue

December 2021 issue

August 2020 issue

April 2020 issue

December 2019 issue

August 2019 issue


Sign up for the latest news

Sign up to our Māngere Pump Station bulletin, so you know what’s happening throughout the project.

May Road - Construction began: August 2019

Location: 54 Roma Road & 105 May Road, Mount Roskill, Auckland 1041


Bulletins

Read the latest issue of the bulletin

July 2024 issue

June 2023 issue

August 2022 issue

December 2021 issue

August 2020 issue

April 2020 issue

December 2019 issue

July 2019 issue


Sign up for the latest news

Sign up to our May Road bulletin, so you know what’s happening throughout the project.

Miranda Reserve incl PS25 - Construction began: 29 September 2020 (Blockhouse Bay Road site) and November 2021 (PS25 site)
Mt Albert War Memorial Reserve - Construction began: May 2022
Norgrove Avenue - Construction began: November 2022

Location: Road - Norgrove Avenue (near 14-16) & 17C Verona Avenue, Mt Albert, Auckland 1025



Bulletins

Read the latest issue of the bulletin

October 2024 issue

May 2024 issue

November 2023 issue

June 2023 issue

October 2022 issue


Sign up for the latest news

Sign up to our Norgrove Avenue bulletin, so you know what’s happening throughout the project.

Rawalpindi Reserve - Construction began: October 2022

Location: 9A Rawalpindi Street, Mt Albert, Auckland 1025



Bulletins

Read the latest bulletin

January 2024 issue

May 2023 issue

September 2022 issue

Sign up for the latest news

Sign up to our Rawalpindi Reserve bulletin, so you know what’s happening throughout the project.

Tawariki Street, Grey Lynn - Construction began: 2023

Location: 44-48 Tawariki Street, Ponsonby, Auckland 1021



Bulletins

Read our latest bulletin

October 2024 issue

October 2023 issue

March 2023 issue


Sign up for the latest news

Sign up to our Tawariki Street bulletin, so you know what’s happening throughout the project.

Walmsley Park - Construction began: December 2020

Location: 727-761 Sandringham Road Extension, Mt Roskill, Auckland 1041


Bulletins

Read our latest Walmsley Park bulletin

November 2022 issue

December 2021 issue

October 2020 issue

February 2020 issue


Sign up for the latest news

Sign up to our Walmsley Park bulletin, so you know what’s happening throughout the project.

Western Springs - Construction began: 2022

Location: 731 Great North Road (Stadium Road), Grey Lynn, Auckland 1021


Bulletins

Read our latest Western Springs bulletin

May 2024 issue

September 2023 issue

September 2022 issue


Sign up for the latest news

Sign up to our Western Springs bulletin, so you know what’s happening throughout the project.

Pt Erin - Construction began: June 2024

Location: Pt Erin Park, 94 Shelley Beach Rd, Herne Bay, Auckland 1011


Bulletins

Read the latest bulletin

June 2024 issue


Sign up for the latest news

Sign up to our Pt Erin bulletin, so you know what’s happening throughout the project.